M.C. CONSULTING
“Quality Communication
Consultations”
Snap: Student Networking and Placement
Team Name: Snap: Student Networking and Placement Report Date: 9/3/09 . Meeting Dates/Times Since Last Report: 8/31 8:00-8:30 p.m,
9/1 2:15-4:00 p.m. (lab time)
Member Absences: None
Summary
of What Was Discussed / Work Done: 8/31: Discussed what we wanted to put in the team
contract, and research. Looked over
research already collected 9/1:
Completed team contract, completed trainees profile Assignments
for Future Work / Deadlines: Keep
doing research, read handout given to us by Professor McGaan, meet and discuss
what we want to ask Chet for visit next lab time Our
Assessment of Our Teamwork Quality and Task Progress (Strengths and
Weaknesses): For
strengths, we all attended the meetings, and we equally worked on the tasks
to get them done and done efficiently.
Also, we already had some research from the Wackerlee
Center. We are not aware of any
weaknesses. Submitted by: _
Jessie Howes_____ |